ITAC Assessment: UM0018
ITAC logo
ITAC Assessment: UM0018
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Brake Rotor and machine engine parts
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 75,000
ft2
Annual Production 1,300,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,120 3,031,360
kWh
Natural Gas $9,579 1,695
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,057 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $4,092 $3,557 $4,092
69,461
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,369 $11,070 $4,369
74,150
kWh
-
03 2.7131: Add area lighting switches $2,577 $1,000 $2,577
43,669
kWh
-
04 2.6218: Turn off equipment when not in use $4,392 - $4,392
74,443
kWh
-
05 2.7231: Use radiant heater for spot heating $1,627 $1,600 - $1,627
-
MMBtu
TOTAL RECOMMENDED $17,057 $17,227 $15,430
261,723
kWh
$1,627
-
MMBtu
TOTAL IMPLEMENTED $15,430 $15,627 $15,430
261,723
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs