ITAC Assessment: UM0004
ITAC logo
ITAC Assessment: UM0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Aluminium Deoxidizers for Steel Production
NAICS
n/a
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 46,000
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,226 1,470,106
kWh
Natural Gas $284,468 77,669
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $108,561 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,253

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $3,971 $3,260 $3,971
44,256
kWh
-
02 2.6218: Turn off equipment when not in use $282 $500 $282
3,224
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,138 $7,537 $7,138
79,426
kWh
-
04 2.2428: Use flue gases in radiant heater for space heating, ovens, etc $82,470 $39,200 - $82,470
-
MMBtu
05 2.1135: Repair furnaces and oven doors so that they seal efficiently $14,700 $3,560 - $14,700
-
MMBtu
TOTAL RECOMMENDED $108,561 $54,057 $11,391
126,906
kWh
$97,170
-
MMBtu
TOTAL IMPLEMENTED $4,253 $3,760 $4,253
47,480
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs