ITAC Assessment: UL2614
ITAC logo
ITAC Assessment: UL2614
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Fruit-based food products
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 55,000
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,653 2,050,560
kWh
Electricity Demand $99,756 4,731
kW-mo/yr
Electricity Fees $25,142 -
Natural Gas $158,583 35,259
MMBtu
Other Gas $14,591 1
MMBtu
Waste Disposal Costs
Water Usage $281,732 32,173
Tgal
TOTAL YEARLY COSTS $653,457
RECOMMENDED SAVINGS* $46,097 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $292 $91 $66
1,844
kWh
$227
-
kW-mo/yr
- -
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $569 $350 $569
14,783
kWh
- - -
03 2.2692: Use outside cold water source as a supply of cooling water $13,075 $57,069 $5,526
153,509
kWh
$7,549
-
kW-mo/yr
- -
04 2.2136: Install / repair insulation on steam lines $2,638 $2,392 - - - $2,638
-
MMBtu
05 2.3212: Optimize plant power factor $3,431 $7,370 - - $3,431 -
06 2.9114: Use solar heat to make electricty $15,745 $220,724 $7,617
213,949
kWh
$8,128
-
kW-mo/yr
- -
07 2.2414: Use waste heat from hot flue gases to preheat $9,873 $32,500 - - - $9,873
-
MMBtu
08 2.4239: Eliminate or reduce compressed air usage $474 $403 $474
13,325
kWh
- - -
TOTAL RECOMMENDED $46,097 $320,899 $14,251
397,410
kWh
$15,904
-
kW-mo/yr
$3,431 $12,511
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs