| Assessment Year | 2026 |
|---|---|
| Principal Product | Aluminum Automotive Parts |
| NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $100 M to 500M |
| # of Employees | 390 |
| Plant Area |
313,800
ft2
|
| Annual Production | 11,195,903
lb
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,366,548 | 21,442,392 |
kWh
|
$0.11 |
| Electricity Demand | $6,621 | 46,188 |
kW-mo/yr
|
$0.14 |
| Electricity Fees | $2,728 | - |
|
- |
| Natural Gas | $565,751 | 98,789 |
MMBtu
|
$5.73 |
| Other Gas | $15,215 | 1 |
MMBtu
|
$15,215.00 |
| TOTAL YEARLY COSTS | $2,956,863 | |||
| RECOMMENDED SAVINGS* | $400,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7292: Lower ceiling to reduce conditioned space | $27,920 | $24,000 |
$27,920
252,899
kWh
|
- | - | |
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $1,596 | $1,000 |
$1,025
9,285
kWh
|
- |
$571
-
MMBtu
|
|
| 03 | 2.2437: Recover waste heat from equipment | $11,262 | $25,000 | - | - |
$11,262
-
MMBtu
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,706 | - |
$8,706
78,859
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,357 | $3,420 |
$15,357
139,105
kWh
|
- | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $127,021 | $112,125 |
$127,021
1,150,546
kWh
|
- | - | |
| 07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $13,403 | $2,331 | - | - |
$13,403
-
MMBtu
|
|
| 08 | 2.2692: Use outside cold water source as a supply of cooling water | $95,772 | $58,367 |
$95,763
867,761
kWh
|
$9
-
kW-mo/yr
|
- | |
| 09 | 2.9114: Use solar heat to make electricty | $99,528 | $621,211 |
$99,520
901,449
kWh
|
$8
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $400,564 | $847,454 |
$375,312
3,399,904
kWh
|
$17
-
kW-mo/yr
|
$25,236
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs