Assessment Year | 2024 |
---|---|
Principal Product | Adhesives and Coatings |
NAICS | 325520: Adhesive Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 38 |
Plant Area |
53,000
ft2
|
Annual Production | 4,200
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,999 | 4,108,520 |
kWh
|
$0.033 |
Electricity Demand | $188,364 | 8,594 |
kW-mo/yr
|
$21.92 |
Electricity Fees | $32,273 | - |
|
- |
Natural Gas | $90,393 | 11,134 |
MMBtu
|
$8.12 |
TOTAL YEARLY COSTS | $445,029 | |||
RECOMMENDED SAVINGS* | $96,925 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $20,797 | $16,250 | - | - | $20,797 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $565 | $273 |
$113
3,439
kWh
|
$452
-
kW-mo/yr
|
- | - | |
03 | 2.7144: Install spectral reflectors / delamp | $276 | - |
$55
1,680
kWh
|
$221
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $139 | $469 |
$139
4,198
kWh
|
- | - | - | |
05 | 2.7292: Lower ceiling to reduce conditioned space | $4,975 | $8,000 |
$4,975
150,743
kWh
|
- | - | - | |
06 | 2.2692: Use outside cold water source as a supply of cooling water | $23,980 | $43,234 |
$10,230
313,658
kWh
|
$13,750
-
kW-mo/yr
|
- | - | |
07 | 2.2136: Install / repair insulation on steam lines | $743 | $660 | - | - | - |
$743
-
MMBtu
|
|
08 | 2.2511: Insulate bare equipment | $1,134 | $330 | - | - | - |
$1,134
-
MMBtu
|
|
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,542 | $1,170 |
$4,542
139,275
kWh
|
- | - | - | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $9,389 | $25,000 | - | - | - |
$9,389
-
MMBtu
|
|
11 | 2.2442: Preheat combustion air with waste heat | $9,389 | $10,000 | - | - | - |
$9,389
-
MMBtu
|
|
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,386 | $1,600 |
$1,386
41,986
kWh
|
- | - | - | |
13 | 2.9114: Use solar heat to make electricty | $19,610 | $190,384 |
$8,782
266,130
kWh
|
$10,828
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $96,925 | $297,370 |
$30,222
921,109
kWh
|
$25,251
-
kW-mo/yr
|
$20,797 |
$20,655
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs