ITAC Assessment: UF0414
ITAC logo
ITAC Assessment: UF0414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product soy milk
NAICS 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing
SIC 2023: Dry, Condensed, and Evaporated Dairy Products
Sales Range $10
M
to 50
M
# of Employees 101
Plant Area 12,000
ft2
Annual Production 17,000,000
pieces
Production Hrs. Annual 8,740
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,928 2,172,221
kWh
Natural Gas $183,384 17,235
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $378,513 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,527 $7,379 $4,527
63,000
kWh
- -
02 2.8212: Reduce delivery schedules $89,700 $6,652 - - $89,700
-
MMBtu
03 2.3212: Optimize plant power factor $44,500 $13,000 $44,500
-
kWh
- -
04 2.4133: Use most efficient type of electric motors $5,808 $15,562 $5,808
75,556
kWh
- -
05 2.7135: Install occupancy sensors $255 $39 $255
3,983
kWh
- -
06 2.2135: Repair and eliminate steam leaks $2,447 $371 - $2,447
-
MMBtu
-
07 2.2441: Preheat boiler makeup water with waste process heat $13,994 $10,000 - $13,994
-
MMBtu
-
08 2.1331: Burn a less expensive grade of fuel $217,282 $100,000 - $217,282
-
MMBtu
-
TOTAL RECOMMENDED $378,513 $153,003 $55,090
142,539
kWh
$233,723
-
MMBtu
$89,700
-
MMBtu
TOTAL IMPLEMENTED $57,537 $36,351 $55,090
142,539
kWh
$2,447
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs