Assessment Year | 2008 |
---|---|
Principal Product | soy milk |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $10 M to 50M |
# of Employees | 101 |
Plant Area |
12,000
ft2
|
Annual Production | 17,000,000
pieces
|
Production Hrs. Annual | 8,740
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $156,928 | 2,172,221 |
kWh
|
$0.072 |
Natural Gas | $183,384 | 17,235 |
MMBtu
|
$10.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $378,513 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,537 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,527 | $7,379 |
$4,527
63,000
kWh
|
- | - | |
02 | 2.8212: Reduce delivery schedules | $89,700 | $6,652 | - | - |
$89,700
-
MMBtu
|
|
03 | 2.3212: Optimize plant power factor | $44,500 | $13,000 |
$44,500
-
kWh
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $5,808 | $15,562 |
$5,808
75,556
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $255 | $39 |
$255
3,983
kWh
|
- | - | |
06 | 2.2135: Repair and eliminate steam leaks | $2,447 | $371 | - |
$2,447
-
MMBtu
|
- | |
07 | 2.2441: Preheat boiler makeup water with waste process heat | $13,994 | $10,000 | - |
$13,994
-
MMBtu
|
- | |
08 | 2.1331: Burn a less expensive grade of fuel | $217,282 | $100,000 | - |
$217,282
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $378,513 | $153,003 |
$55,090
142,539
kWh
|
$233,723
-
MMBtu
|
$89,700
-
MMBtu
|
||
TOTAL IMPLEMENTED | $57,537 | $36,351 |
$55,090
142,539
kWh
|
$2,447
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs