| Assessment Year | 2024 |
|---|---|
| Principal Product | Automotive Parts |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $100 M to 500M |
| # of Employees | 450 |
| Plant Area |
820,000
ft2
|
| Annual Production | 10,000,000
pieces
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $508,117 | 17,753,900 |
kWh
|
$0.029 |
| Electricity Demand | $755,054 | 36,302 |
kW-mo/yr
|
$20.80 |
| Electricity Fees | $317,231 | - |
|
- |
| Natural Gas | $395,917 | 55,452 |
MMBtu
|
$7.14 |
| TOTAL YEARLY COSTS | $1,976,319 | |||
| RECOMMENDED SAVINGS* | $419,079 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $50,786 | $33,072 | - | - | $50,786 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,084 | $419 |
$269
9,393
kWh
|
$815
-
kW-mo/yr
|
- | - | |
| 03 | 2.7144: Install spectral reflectors / delamp | $1,516 | - |
$385
13,465
kWh
|
$1,131
-
kW-mo/yr
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $5,080 | $13,000 | - | - | - |
$5,080
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $4,523 | $13,000 | - | - | - |
$4,523
-
MMBtu
|
|
| 06 | 2.2692: Use outside cold water source as a supply of cooling water | $5,809 | $43,234 |
$1,376
48,084
kWh
|
$4,433
-
kW-mo/yr
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,250 | $840 |
$1,250
43,660
kWh
|
- | - | - | |
| 08 | 2.4235: Remove or close off unneeded compressed air lines | $24,490 | $4,200 |
$10,095
352,959
kWh
|
$14,395
-
kW-mo/yr
|
- | - | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,134 | $16,300 |
$4,134
144,541
kWh
|
- | - | - | |
| 10 | 2.9114: Use solar heat to make electricty | $320,407 | $3,432,213 |
$135,179
4,726,522
kWh
|
$185,228
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $419,079 | $3,556,278 |
$152,688
5,338,624
kWh
|
$206,002
-
kW-mo/yr
|
$50,786 |
$9,603
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs