Assessment Year | 2024 |
---|---|
Principal Product | Pet Bedding |
NAICS | 321219: Reconstituted Wood Product Manufacturing |
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 91 |
Plant Area |
250,000
ft2
|
Annual Production | 64,067
ton
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $253,320 | 7,419,760 |
kWh
|
$0.034 |
Electricity Demand | $423,563 | 20,773 |
kW-mo/yr
|
$20.39 |
Electricity Fees | $139,961 | - |
|
- |
Natural Gas | $400,772 | 74,556 |
MMBtu
|
$5.38 |
TOTAL YEARLY COSTS | $1,217,616 | |||
RECOMMENDED SAVINGS* | $137,635 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $35,606 | $77,327 | - | - | - |
$35,606
-
MMBtu
|
|
02 | 2.3212: Optimize plant power factor | $32,359 | $12,025 | - | - | $32,359 | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,407 | $9,750 |
$3,407
99,784
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,803 | - |
$1,803
52,827
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,498 | $1,785 |
$4,498
131,759
kWh
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $181 | $779 |
$181
5,309
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,568 | $3,839 |
$2,845
83,319
kWh
|
$2,723
-
kW-mo/yr
|
- | - | |
08 | 2.7144: Install spectral reflectors / delamp | $680 | - |
$294
8,601
kWh
|
$386
-
kW-mo/yr
|
- | - | |
09 | 2.9114: Use solar heat to make electricty | $53,533 | $548,395 |
$24,521
718,252
kWh
|
$29,012
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $137,635 | $653,900 |
$37,549
1,099,851
kWh
|
$32,121
-
kW-mo/yr
|
$32,359 |
$35,606
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs