Assessment Year | 2023 |
---|---|
Principal Product | Filters and Filter Media |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 143 |
Plant Area |
232,256
ft2
|
Annual Production | 10,617,486
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $393,219 | 4,846,682 |
kWh
|
$0.081 | |
Electricity Demand | $148,679 | 10,867 |
kW-mo/yr
|
$13.68 | |
Electricity Fees | $53,166 | - |
|
- | |
Natural Gas | $128,094 | 14,709 |
MMBtu
|
$8.71 | |
Waste Disposal Costs | |||||
Water Usage | $17,334 | 37 |
Tgal
|
$467.32 | |
Water Disposal | $24,889 | 37 |
Tgal
|
$671.01 | |
TOTAL YEARLY COSTS | $765,381 | ||||
RECOMMENDED SAVINGS* | $313,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $145,022 | $23,878 |
$121,046
1,494,397
kWh
|
$23,976
-
kW-mo/yr
|
|
02 | 2.7111: Reduce illumination to minimum necessary levels | $4,283 | - |
$2,598
32,021
kWh
|
$1,685
-
kW-mo/yr
|
|
03 | 2.9114: Use solar heat to make electricty | $159,497 | $1,065,693 |
$121,666
1,499,617
kWh
|
$37,831
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,462 | - |
$2,462
30,394
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,694 | $540 |
$1,694
20,908
kWh
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $550 | $2,438 |
$550
6,776
kWh
|
- | |
TOTAL RECOMMENDED | $313,508 | $1,092,549 |
$250,016
3,084,113
kWh
|
$63,492
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs