ITAC Assessment: AM0691
ITAC logo
ITAC Assessment: AM0691
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Steel fabrication
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $5
M
to 10
M
# of Employees 56
Plant Area 157,000
ft2
Annual Production 3,100
ton
Production Hrs. Annual 2,331
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,890 1,236,000
kWh
Electricity Demand $34,395 4,086
kW-mo/yr
Electricity Fees $2,539 -
Natural Gas $1,708 215
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,200 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,270

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $25,140 $39,720 $14,790
242,400
kWh
$10,350
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,550 $2,000 $2,680
43,900
kWh
$1,870
-
kW-mo/yr
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,250 $1,720 $740
12,130
kWh
$510
-
kW-mo/yr
04 2.6218: Turn off equipment when not in use $440 - $440
7,240
kWh
-
05 2.7135: Install occupancy sensors $420 $240 $420
6,840
kWh
-
06 2.7134: Use photocell controls $280 $130 $200
3,320
kWh
$80
-
kW-mo/yr
07 2.7121: Utilize daylight whenever possible in lieu of artificial light $120 $130 $120
2,000
kWh
-
TOTAL RECOMMENDED $32,200 $43,940 $19,390
317,830
kWh
$12,810
-
kW-mo/yr
TOTAL IMPLEMENTED $5,270 $2,130 $3,320
54,460
kWh
$1,950
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs