Assessment Year | 2015 |
---|---|
Principal Product | Steel fabrication |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $5 M to 10M |
# of Employees | 56 |
Plant Area |
157,000
ft2
|
Annual Production | 3,100
ton
|
Production Hrs. Annual | 2,331
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,890 | 1,236,000 |
kWh
|
$0.061 |
Electricity Demand | $34,395 | 4,086 |
kW-mo/yr
|
$8.42 |
Electricity Fees | $2,539 | - |
|
- |
Natural Gas | $1,708 | 215 |
MMBtu
|
$7.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,200 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,270 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,140 | $39,720 |
$14,790
242,400
kWh
|
$10,350
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,550 | $2,000 |
$2,680
43,900
kWh
|
$1,870
-
kW-mo/yr
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,250 | $1,720 |
$740
12,130
kWh
|
$510
-
kW-mo/yr
|
|
04 | 2.6218: Turn off equipment when not in use | $440 | - |
$440
7,240
kWh
|
- | |
05 | 2.7135: Install occupancy sensors | $420 | $240 |
$420
6,840
kWh
|
- | |
06 | 2.7134: Use photocell controls | $280 | $130 |
$200
3,320
kWh
|
$80
-
kW-mo/yr
|
|
07 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $120 | $130 |
$120
2,000
kWh
|
- | |
TOTAL RECOMMENDED | $32,200 | $43,940 |
$19,390
317,830
kWh
|
$12,810
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $5,270 | $2,130 |
$3,320
54,460
kWh
|
$1,950
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs