ITAC Assessment: UL2307
ITAC logo
ITAC Assessment: UL2307
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Copper-Nickel Alloys
NAICS 331110: Iron and Steel Mills and Ferroalloy Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 150,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,726 8,322,120
kWh
Electricity Demand $394,121 18,551
kW-mo/yr
Electricity Fees $157,720 -
Natural Gas $464,379 39,639
MMBtu
Waste Disposal Costs
Water Usage $37,018 7,388
Tgal
Water Disposal $78,724 12,888
Tgal
TOTAL YEARLY COSTS $1,345,688
RECOMMENDED SAVINGS* $183,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $53,544

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7135: Install occupancy sensors $1,100 $2,693 $1,100
42,311
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,654 $33,973 $6,719
306,251
kWh
$8,935
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,834 - $1,834
70,546
kWh
- - -
04 2.3212: Optimize plant power factor $38,660 $22,666 - - - $38,660
05 2.9114: Use solar heat to make electricty $38,855 $480,889 $12,347
480,748
kWh
$26,508
-
kW-mo/yr
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,752 $14,626 $4,752
162,006
kWh
- - -
07 2.7491: Insulate glazing, walls, ceilings, and roofs $36,790 $34,740 - - $36,790
-
MMBtu
-
08 2.2437: Recover waste heat from equipment $46,192 $39,000 - - $46,192
-
MMBtu
-
TOTAL RECOMMENDED $183,837 $628,587 $26,752
1,061,862
kWh
$35,443
-
kW-mo/yr
$82,982
-
MMBtu
$38,660
TOTAL IMPLEMENTED $53,544 $71,406 $7,819
348,562
kWh
$8,935
-
kW-mo/yr
$36,790
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs