Assessment Year | 2023 |
---|---|
Principal Product | Baking mixes |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 258 |
Plant Area |
150,000
ft2
|
Annual Production | 71,344
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $442,321 | 14,213,280 |
kWh
|
$0.031 | |
Electricity Demand | $741,602 | 28,971 |
kW-mo/yr
|
$25.60 | |
Electricity Fees | $170,716 | - |
|
- | |
Natural Gas | $297,336 | 42,590 |
MMBtu
|
$6.98 | |
Waste Disposal Costs | |||||
Water Usage | $45,169 | 10,153 |
Tgal
|
$4.45 | |
TOTAL YEARLY COSTS | $1,697,144 | ||||
RECOMMENDED SAVINGS* | $122,910 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $43,641 | $26,163 | - | - | $43,641 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,504 | - |
$2,775
89,183
kWh
|
$5,729
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,439 | $34,126 |
$6,200
199,970
kWh
|
$10,239
-
kW-mo/yr
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $4,140 | $7,650 | - | - | - |
$4,140
-
MMBtu
|
|
05 | 2.9114: Use solar heat to make electricty | $36,831 | $336,395 |
$14,489
465,573
kWh
|
$22,342
-
kW-mo/yr
|
- | - | |
06 | 2.7273: Install desiccant humidity control system | $7,161 | $21,450 | - |
$7,161
-
kW-mo/yr
|
- | - | |
07 | 2.2692: Use outside cold water source as a supply of cooling water | $6,194 | $25,900 |
$6,194
199,800
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $122,910 | $451,684 |
$29,658
954,526
kWh
|
$45,471
-
kW-mo/yr
|
$43,641 |
$4,140
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs