| Assessment Year | 2022 |
|---|---|
| Principal Product | Flat Roll Steel |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $5 M to 10M |
| # of Employees | 38 |
| Plant Area |
100,000
ft2
|
| Annual Production | 116,650
ton
|
| Production Hrs. Annual | 7,800
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,689 | 937,200 |
kWh
|
$0.030 |
| Electricity Demand | $79,511 | 3,728 |
kW-mo/yr
|
$21.33 |
| Electricity Fees | $9,361 | - |
|
- |
| Natural Gas | $39,109 | 3,085 |
MMBtu
|
$12.68 |
| TOTAL YEARLY COSTS | $155,670 | |||
| RECOMMENDED SAVINGS* | $65,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $47,633 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $11,500 | - | - | - | $11,500 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $700 | $562 |
$332
11,243
kWh
|
$368
-
kW-mo/yr
|
- | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,339 | - |
$659
22,310
kWh
|
$680
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $124 | $564 |
$124
4,193
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,734 | $1,440 |
$1,734
58,701
kWh
|
- | - | - | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $447 | - |
$84
2,844
kWh
|
- | - |
$363
-
MMBtu
|
|
| 07 | 2.4133: Use most efficient type of electric motors | $4,277 | $10,869 |
$430
14,554
kWh
|
$3,847
-
kW-mo/yr
|
- | - | |
| 08 | 2.9114: Use solar heat to make electricty | $45,075 | $458,134 |
$19,721
667,609
kWh
|
$25,354
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $65,196 | $471,569 |
$23,084
781,454
kWh
|
$30,249
-
kW-mo/yr
|
$11,500 |
$363
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $47,633 | $460,700 |
$21,911
741,746
kWh
|
$25,722
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs