ITAC Assessment: UL2213
ITAC logo
ITAC Assessment: UL2213
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Flat Roll Steel
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 38
Plant Area 100,000
ft2
Annual Production 116,650
ton
Production Hrs. Annual 7,800
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,689 937,200
kWh
Electricity Demand $79,511 3,728
kW-mo/yr
Electricity Fees $9,361 -
Natural Gas $39,109 3,085
MMBtu
TOTAL YEARLY COSTS $155,670
RECOMMENDED SAVINGS* $65,196 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,633

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.8114: Change rate schedules or other changes in utility service $11,500 - - - $11,500 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $700 $562 $332
11,243
kWh
$368
-
kW-mo/yr
- -
03 2.7111: Reduce illumination to minimum necessary levels $1,339 - $659
22,310
kWh
$680
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $124 $564 $124
4,193
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,734 $1,440 $1,734
58,701
kWh
- - -
06 2.7221: Lower temperature during the winter season and vice-versa $447 - $84
2,844
kWh
- - $363
-
MMBtu
07 2.4133: Use most efficient type of electric motors $4,277 $10,869 $430
14,554
kWh
$3,847
-
kW-mo/yr
- -
08 2.9114: Use solar heat to make electricty $45,075 $458,134 $19,721
667,609
kWh
$25,354
-
kW-mo/yr
- -
TOTAL RECOMMENDED $65,196 $471,569 $23,084
781,454
kWh
$30,249
-
kW-mo/yr
$11,500 $363
-
MMBtu
TOTAL IMPLEMENTED $47,633 $460,700 $21,911
741,746
kWh
$25,722
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs