ITAC Assessment: UL2211
ITAC logo
ITAC Assessment: UL2211
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Metal Industrial Components
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 167,000
ft2
Annual Production 8,713,045
units
Production Hrs. Annual 7,488
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $666,671 10,554,600
kWh
Electricity Demand $256,296 21,333
kW-mo/yr
Electricity Fees $(-259,812.0) -
Natural Gas $61,518 50,239
MMBtu
TOTAL YEARLY COSTS $724,673
RECOMMENDED SAVINGS* $234,269 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,467

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,600 $15,000 $2,600
41,164
kWh
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,806 $20,000 $4,806
76,081
kWh
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,815 - $1,815
28,812
kWh
- - -
04 2.3212: Optimize plant power factor $61,887 $45,461 - - $61,887 -
05 2.9114: Use solar heat to make electricty $96,458 $783,531 $72,042
1,143,517
kWh
$24,416
-
kW-mo/yr
- -
06 2.9112: Use solar heat to heat water $60,938 $150,000 - - - $60,938
-
MMBtu
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,765 - - $5,765
-
kW-mo/yr
- -
TOTAL RECOMMENDED $234,269 $1,013,992 $81,263
1,289,574
kWh
$30,181
-
kW-mo/yr
$61,887 $60,938
-
MMBtu
TOTAL IMPLEMENTED $69,467 $45,461 $1,815
28,812
kWh
$5,765
-
kW-mo/yr
$61,887 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs