Assessment Year | 2022 |
---|---|
Principal Product | Metal Industrial Components |
NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 300 |
Plant Area |
167,000
ft2
|
Annual Production | 8,713,045
units
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $666,671 | 10,554,600 |
kWh
|
$0.063 |
Electricity Demand | $256,296 | 21,333 |
kW-mo/yr
|
$12.01 |
Electricity Fees | $(-259,812.0) | - |
|
- |
Natural Gas | $61,518 | 50,239 |
MMBtu
|
$1.22 |
TOTAL YEARLY COSTS | $724,673 | |||
RECOMMENDED SAVINGS* | $234,269 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,467 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,600 | $15,000 |
$2,600
41,164
kWh
|
- | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,806 | $20,000 |
$4,806
76,081
kWh
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,815 | - |
$1,815
28,812
kWh
|
- | - | - | |
04 | 2.3212: Optimize plant power factor | $61,887 | $45,461 | - | - | $61,887 | - | |
05 | 2.9114: Use solar heat to make electricty | $96,458 | $783,531 |
$72,042
1,143,517
kWh
|
$24,416
-
kW-mo/yr
|
- | - | |
06 | 2.9112: Use solar heat to heat water | $60,938 | $150,000 | - | - | - |
$60,938
-
MMBtu
|
|
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,765 | - | - |
$5,765
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $234,269 | $1,013,992 |
$81,263
1,289,574
kWh
|
$30,181
-
kW-mo/yr
|
$61,887 |
$60,938
-
MMBtu
|
||
TOTAL IMPLEMENTED | $69,467 | $45,461 |
$1,815
28,812
kWh
|
$5,765
-
kW-mo/yr
|
$61,887 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs