ITAC Assessment: UL0249
ITAC logo
ITAC Assessment: UL0249
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Barge port service
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 118
Plant Area 43,560
ft2
Annual Production 1,500
pieces
Production Hrs. Annual 3,600
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,822 5,094,360
kWh
Electricity Demand $68,282 13,501
kW-mo/yr
Electricity Fees $28,305 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,026 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,950

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7145: Install skylights $4,840 $5,700 $4,840
138,265
kWh
- - - -
02 2.6218: Turn off equipment when not in use $1,210 - $1,210
35,463
kWh
- - - -
03 3.4151: Minimize water usage $3,539 $909 - - $3,782
-
Tgal
- $(-243.0)
04 3.8136: Switch to a solvent that can be cleaned and re-used $1,537 $700 - - - $1,537
-
lb
-
05 2.8112: Combine utility meters $3,900 $5,000 - $3,900 - - -
TOTAL RECOMMENDED $15,026 $12,309 $6,050
173,728
kWh
$3,900 $3,782
-
Tgal
$1,537
-
lb
$(-243.0)
TOTAL IMPLEMENTED $9,950 $10,700 $6,050
173,728
kWh
$3,900 - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs