Assessment Year | 2000 |
---|---|
Principal Product | Steel Nails, Spikes & Wiredrawing |
NAICS |
n/a
|
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | n/a |
# of Employees | 83 |
Plant Area |
300,000
ft2
|
Annual Production | 45,000
ton
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $674,740 | 25,394,783 |
kWh
|
$0.027 |
Electricity Demand | $235,696 | 40,449 |
kW-mo/yr
|
$5.83 |
Natural Gas | $285,885 | 91,505 |
MMBtu
|
$3.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,322 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,291 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $6,743 | - | - | $6,743 | - | |
02 | 2.7122: Disconnect ballasts | $12,291 | $1,236 |
$12,291
462,192
kWh
|
- | - | |
03 | 4.322: Eliminate old stock and modify inventory control | $15,288 | $80,000 | - | - | $15,288 | |
TOTAL RECOMMENDED | $34,322 | $81,236 |
$12,291
462,192
kWh
|
$6,743 | $15,288 | ||
TOTAL IMPLEMENTED | $12,291 | $1,236 |
$12,291
462,192
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs