ITAC Assessment: UL0236
ITAC logo
ITAC Assessment: UL0236
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Ice Cream and Ice Desserts
NAICS
n/a
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 26,000
ft2
Annual Production 1,800
Tgal
Production Hrs. Annual 1,920
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,352 1,439,625
kWh
Electricity Demand $26,020 3,080
kW-mo/yr
Natural Gas $22,348 4,749
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $55,240 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,472 $20 $792
20,516
kWh
$680
-
kW-mo/yr
- -
02 3.7134: Wash and reuse rags on-site $5,446 $11,315 - - - $5,446
03 4.441: Install automatic packing equipment $48,322 $66,150 - - $29,952 $18,370
TOTAL RECOMMENDED $55,240 $77,485 $792
20,516
kWh
$680
-
kW-mo/yr
$29,952 $23,816
TOTAL IMPLEMENTED $1,472 $20 $792
20,516
kWh
$680
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs