ITAC Assessment: UL0228
ITAC logo
ITAC Assessment: UL0228
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Air Filters
NAICS
n/a
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 329,000
ft2
Annual Production 28,000,000
pieces
Production Hrs. Annual 7,344
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,092 2,321,219
kWh
Electricity Demand $62,640 5,491
kW-mo/yr
Electricity Fees $4,457 -
Natural Gas $13,812 2,127
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $417,890 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,001 $20 $937
57,151
kWh
$1,064
-
kW-mo/yr
- - -
02 3.6192: Use a less expensive method of waste removal $8,550 - - - - - $8,550
03 3.5212: Regrind, reuse, or sell scrap plastic parts $9,641 $10,400 - - - - $9,641
04 3.1162: Use less wasteful packaging $58,958 $1,000 - - - $32,288 $26,670
05 4.441: Install automatic packing equipment $88,740 $1,560 - - $88,740 - -
06 4.311: Schedule deliveries according to demand $250,000 - - - - - $250,000
TOTAL RECOMMENDED $417,890 $12,980 $937
57,151
kWh
$1,064
-
kW-mo/yr
$88,740 $32,288 $294,861
TOTAL IMPLEMENTED $2,001 $20 $937
57,151
kWh
$1,064
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs