| Assessment Year | 1999 |
|---|---|
| Principal Product | Air Filters |
| NAICS |
n/a
|
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
329,000
ft2
|
| Annual Production | 28,000,000
pieces
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $38,092 | 2,321,219 |
kWh
|
$0.016 |
| Electricity Demand | $62,640 | 5,491 |
kW-mo/yr
|
$11.41 |
| Electricity Fees | $4,457 | - |
|
- |
| Natural Gas | $13,812 | 2,127 |
MMBtu
|
$6.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $417,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,001 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,001 | $20 |
$937
57,151
kWh
|
$1,064
-
kW-mo/yr
|
- | - | - | |
| 02 | 3.6192: Use a less expensive method of waste removal | $8,550 | - | - | - | - | - | $8,550 | |
| 03 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $9,641 | $10,400 | - | - | - | - | $9,641 | |
| 04 | 3.1162: Use less wasteful packaging | $58,958 | $1,000 | - | - | - | $32,288 | $26,670 | |
| 05 | 4.441: Install automatic packing equipment | $88,740 | $1,560 | - | - | $88,740 | - | - | |
| 06 | 4.311: Schedule deliveries according to demand | $250,000 | - | - | - | - | - | $250,000 | |
| TOTAL RECOMMENDED | $417,890 | $12,980 |
$937
57,151
kWh
|
$1,064
-
kW-mo/yr
|
$88,740 | $32,288 | $294,861 | ||
| TOTAL IMPLEMENTED | $2,001 | $20 |
$937
57,151
kWh
|
$1,064
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs