ITAC Assessment: UL0227
ITAC logo
ITAC Assessment: UL0227
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Drawing and Insulating of Nonferrous Wire
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 340,000
ft2
Annual Production 48,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $954,185 46,400,939
kWh
Electricity Demand $403,518 155,905
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $426,078 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 3.5311: Recover and reuse waste material $43,200 $5,000 - - $43,200 -
02 3.5315: Lease / purchase baler; sell cardboard to recycler $48,094 $8,165 $20,270
-
lb
- $27,824 -
03 3.5212: Regrind, reuse, or sell scrap plastic parts $10,644 - - - $10,644 -
04 4.454: Modify startup/shutdown times $318,710 $533,131 - $318,710 - -
05 4.513: Re-arrange equipment layout to reduce labor costs $5,430 $1,799 - - - $5,430
TOTAL RECOMMENDED $426,078 $548,095 $20,270
-
lb
$318,710 $81,668 $5,430
TOTAL IMPLEMENTED $5,430 $1,799 - - - $5,430
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs