Assessment Year | 1999 |
---|---|
Principal Product | air brake components for large trucks |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 378 |
Plant Area |
180,000
ft2
|
Annual Production | 9,000,000,000
pieces
|
Production Hrs. Annual | 8,592
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $317,746 | 14,267,585 |
kWh
|
$0.022 |
Electricity Demand | $127,063 | 23,141 |
kW-mo/yr
|
$5.49 |
Natural Gas | $20,656 | 10,205 |
MMBtu
|
$2.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $649,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $8,888 | $54,400 | n/a | - | - |
$8,888
-
MMBtu
|
- | - | - | - |
02 | 2.7111: Reduce illumination to minimum necessary levels | $12,793 | $960 | n/a |
$7,521
337,339
kWh
|
$2,536
-
kW-mo/yr
|
- | - | - | $360 | $2,376 |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,065 | $20 | n/a |
$790
55,686
kWh
|
$275
-
kW-mo/yr
|
- | - | - | - | - |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $26,207 | $8,168 | n/a | - | - | - |
$26,207
-
lb
|
- | - | - |
05 | 4.821: Pay bills on time to avoid late fees | $1,142 | - | n/a | - | - | - | - | - | - | $1,142 |
06 | 4.431: Train operators for maximum operating efficiency | $599,716 | $24,482 | n/a | - | - | - | - | $599,716 | - | - |
TOTAL RECOMMENDED | $649,811 | $88,030 |
$8,311
393,025
kWh
|
$2,811
-
kW-mo/yr
|
$8,888
-
MMBtu
|
$26,207
-
lb
|
$599,716 | $360 | $3,518 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs