ITAC Assessment: UL0199
ITAC logo
ITAC Assessment: UL0199
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Automotive Gears
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 152,150
ft2
Annual Production 25,400,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $558,423 15,140,094
kWh
Electricity Demand $309,599 29,235
kW-mo/yr
Natural Gas $801,441 220,429
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,929 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $6,970 $10,350 $4,363
118,113
kWh
$2,607
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $6,343 $20 $3,971
107,562
kWh
$2,372
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,416 $20,821 $2,746
74,443
kWh
$2,670
-
kW-mo/yr
-
04 3.5316: Contract a wood pallet recycling company $2,400 - - - $2,400
-
lb
05 3.5315: Lease / purchase baler; sell cardboard to recycler $3,750 - - - $3,750
-
lb
06 3.5248: Separate and recycle scrap metal to foundry or for sale $3,050 - - - $3,050
-
lb
TOTAL RECOMMENDED $27,929 $31,191 $11,080
300,118
kWh
$7,649
-
kW-mo/yr
$9,200
-
lb
TOTAL IMPLEMENTED $17,063 $10,370 $8,334
225,675
kWh
$4,979
-
kW-mo/yr
$3,750
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs