| Assessment Year | 1997 |
|---|---|
| Principal Product | Plastic Automotive and Decorative Trim |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 185 |
| Plant Area |
62,000
ft2
|
| Annual Production | 480,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,596 | 5,162,954 |
kWh
|
$0.024 |
| Electricity Demand | $67,780 | 12,008 |
kW-mo/yr
|
$5.64 |
| Natural Gas | $45,584 | 9,164 |
MMBtu
|
$4.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,483 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4321: Upgrade obsolete equipment | $139 | - |
$139
5,862
kWh
|
- | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $350 | $8,500 |
$253
10,551
kWh
|
$97
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $3,388 | $786 |
$4,459
186,694
kWh
|
$1,396
-
kW-mo/yr
|
$(-2,467.0)
-
MMBtu
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $415 | $263 | - | - |
$415
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $476 | $3,157 |
$319
13,189
kWh
|
$157
-
kW-mo/yr
|
- | - | - | |
| 06 | 3.8141: Regenerate cleaning solvent on-site and reuse | $19,550 | $56,265 | - | - | - |
$19,550
-
gal
|
- | |
| 07 | 3.3126: Use absorption, extraction to remove contaminants | $5,165 | $60 | - | - | - | - |
$5,165
-
lb
|
|
| TOTAL RECOMMENDED | $29,483 | $69,031 |
$5,170
216,296
kWh
|
$1,650
-
kW-mo/yr
|
$(-2,052.0)
-
MMBtu
|
$19,550
-
gal
|
$5,165
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs