ITAC Assessment: UL0171
ITAC logo
ITAC Assessment: UL0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Business Cards, Labels, and Letterheads
NAICS
n/a
SIC 2799:
Sales Range $10
M
to 50
M
# of Employees 591
Plant Area 170,000
ft2
Annual Production 608,000
pieces
Production Hrs. Annual 6,550
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,630 3,934,056
kWh
Electricity Demand $77,694 8,742
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,728 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,323

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $100 $3,020 $32
1,465
kWh
$68
-
kW-mo/yr
- - -
02 2.3212: Optimize plant power factor $5,423 $6,179 - $5,423
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $195 $20 $62
2,638
kWh
$133
-
kW-mo/yr
- - -
04 3.5311: Recover and reuse waste material $1,860 - - - $1,860
-
lb
- -
05 3.1191: Change procedures / equipment / operating conditions $20,800 - - - - - $20,800
06 3.7134: Wash and reuse rags on-site $29,350 $4,300 - - - $29,350 -
TOTAL RECOMMENDED $57,728 $13,519 $94
4,103
kWh
$5,624
-
kW-mo/yr
$1,860
-
lb
$29,350 $20,800
TOTAL IMPLEMENTED $26,323 $9,199 $32
1,465
kWh
$5,491
-
kW-mo/yr
- - $20,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs