Assessment Year | 1996 |
---|---|
Principal Product | Vinyl Wall Coverings |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
52,000
ft2
|
Annual Production | 44,550
thousand feet
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,579 | 882,474 |
kWh
|
$0.024 |
Electricity Demand | $31,259 | 3,154 |
kW-mo/yr
|
$9.91 |
Electricity Fees | $2,034 | - |
|
- |
Natural Gas | $24,611 | 6,288 |
MMBtu
|
$3.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,228 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,852 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,726 | $7,330 | - |
$6,726
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $937 | $636 |
$561
22,860
kWh
|
$376
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $199 | $20 |
$127
5,275
kWh
|
$72
-
kW-mo/yr
|
- | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $3,360 | $200 | - | - | - |
$3,360
-
lb
|
- | |
05 | 3.7131: Use a rag recycle service | $3,217 | $2,200 | - | - |
$3,217
-
lb
|
- | - | |
06 | 4.222: Purchase re-conditioned material instead of new | $960 | - | - | - | - | - | $960 | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,829 | $1,500 | - | - |
$1,829
-
lb
|
- | - | |
TOTAL RECOMMENDED | $17,228 | $11,886 |
$688
28,135
kWh
|
$7,174
-
kW-mo/yr
|
$5,046
-
lb
|
$3,360
-
lb
|
$960 | ||
TOTAL IMPLEMENTED | $12,852 | $9,666 |
$561
22,860
kWh
|
$7,102
-
kW-mo/yr
|
$1,829
-
lb
|
$3,360
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs