ITAC Assessment: UL0162
ITAC logo
ITAC Assessment: UL0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Wood Office Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 133,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,139 191,383
kWh
Electricity Demand $56,020 18,673
kW-mo/yr
Natural Gas $17,227 3,616
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $194,636 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $187,929

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Raw Material Savings
01 2.4133: Use most efficient type of electric motors $208 $2,990 $165
2,345
kWh
$43
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,308 $1,307 $1,034
14,947
kWh
$274
-
kW-mo/yr
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $324 $84 $240
3,517
kWh
$84
-
kW-mo/yr
- - - -
04 3.1191: Change procedures / equipment / operating conditions $6,707 - - - - $160
-
lb
$3,042 $3,505
05 3.1191: Change procedures / equipment / operating conditions $186,089 $31,000 - - $3,841 $129
-
lb
$33,547 $148,572
TOTAL RECOMMENDED $194,636 $35,381 $1,439
20,809
kWh
$401
-
kW-mo/yr
$3,841 $289
-
lb
$36,589 $152,077
TOTAL IMPLEMENTED $187,929 $35,381 $1,439
20,809
kWh
$401
-
kW-mo/yr
$3,841 $129
-
lb
$33,547 $148,572
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs