| Assessment Year | 1996 |
|---|---|
| Principal Product | Diesel Engine Components and Inflatable Restraints |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
450,000
ft2
|
| Annual Production | 20,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $209,092 | 12,067,702 |
kWh
|
$0.017 |
| Electricity Demand | $237,949 | 24,998 |
kW-mo/yr
|
$9.52 |
| Natural Gas | $411,770 | 122,457 |
MMBtu
|
$3.36 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,857 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,706 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,663 | $25,452 |
$2,667
153,869
kWh
|
$1,996
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,585 | $20 |
$757
43,669
kWh
|
$828
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,403 | $2,000 | - | - |
$5,403
-
MMBtu
|
- | - | - | |
| 04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $5,000 | - | - | - | - | - | - |
$5,000
-
lb
|
|
| 05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $770 | - | - | - | - | - | - |
$770
-
lb
|
|
| 06 | 3.4155: Meter waste water | $26,500 | $3,500 | - | - | - |
$26,500
-
Tgal
|
- | - | |
| 07 | 3.8142: Distill contaminated solvents for reuse | $29,936 | $16,000 | - | - | - | - |
$22,700
-
gal
|
$7,236
-
lb
|
|
| TOTAL RECOMMENDED | $73,857 | $46,972 |
$3,424
197,538
kWh
|
$2,824
-
kW-mo/yr
|
$5,403
-
MMBtu
|
$26,500
-
Tgal
|
$22,700
-
gal
|
$13,006
-
lb
|
||
| TOTAL IMPLEMENTED | $30,706 | $16,000 | - | - | - | - |
$22,700
-
gal
|
$8,006
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs