Assessment Year | 1996 |
---|---|
Principal Product | Bakery Products |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
108,000
ft2
|
Annual Production | 39,000,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,618 | 4,264,068 |
kWh
|
$0.025 |
Electricity Demand | $86,206 | 8,633 |
kW-mo/yr
|
$9.99 |
Electricity Fees | $1,850 | - |
|
- |
Natural Gas | $150,531 | 43,637 |
MMBtu
|
$3.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,752 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,550 | $4,024 |
$1,912
75,029
kWh
|
$1,638
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,644 | $3,850 |
$863
33,998
kWh
|
$781
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,558 | $2,000 | - | - | - |
$1,558
-
MMBtu
|
- | - | |
04 | 2.3212: Optimize plant power factor | $5,523 | $14,000 | - | - | $5,523 | - | - | - | |
05 | 3.5311: Recover and reuse waste material | $4,690 | - | - | - | - | - |
$1,240
-
lb
|
$3,450 | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $3,378 | $520 | - | - | - | - |
$1,620
-
lb
|
$1,758 | |
07 | 3.5313: Increase amount of waste recovered for resale | $24,000 | $100 | - | - | - | - |
$1,000
-
lb
|
$23,000 | |
TOTAL RECOMMENDED | $44,343 | $24,494 |
$2,775
109,027
kWh
|
$2,419
-
kW-mo/yr
|
$5,523 |
$1,558
-
MMBtu
|
$3,860
-
lb
|
$28,208 | ||
TOTAL IMPLEMENTED | $6,752 | $9,874 |
$2,775
109,027
kWh
|
$2,419
-
kW-mo/yr
|
- |
$1,558
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs