Assessment Year | 2020 |
---|---|
Principal Product | Dairy Products, Tea, and Fruit Juice |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $100 M to 500M |
# of Employees | 183 |
Plant Area |
126,000
ft2
|
Annual Production | 449,857,161
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $403,346 | 14,448,000 |
kWh
|
$0.028 | |
Electricity Demand | $635,056 | 35,247 |
kW-mo/yr
|
$18.02 | |
Electricity Fees | $23,316 | - |
|
- | |
Natural Gas | $219,748 | 70,062 |
MMBtu
|
$3.14 | |
Waste Disposal Costs | |||||
Water Usage | $366,141 | 90,360 |
Tgal
|
$4.05 | |
Water Disposal | $447,431 | 41,936 |
Tgal
|
$10.67 | |
TOTAL YEARLY COSTS | $2,095,038 | ||||
RECOMMENDED SAVINGS* | $447,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $22,557 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,076 | $2,010 |
$4,292
153,300
kWh
|
$3,784
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,413 | - |
$512
18,287
kWh
|
$901
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,887 | $9,378 |
$5,259
187,814
kWh
|
$4,628
-
kW-mo/yr
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $571 | $875 |
$571
20,386
kWh
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,684 | $2,240 |
$3,819
136,400
kWh
|
$4,865
-
kW-mo/yr
|
- | - | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $118,102 | $6,775 | - | - | - | - |
$118,102
-
Tgal
|
|
07 | 2.2615: Clean condenser tubes | $4,023 | $8,700 |
$4,023
143,696
kWh
|
- | - | - | - | |
08 | 2.2511: Insulate bare equipment | $2,547 | $1,006 |
$736
26,280
kWh
|
$973
-
kW-mo/yr
|
- |
$838
-
MMBtu
|
- | |
09 | 2.2444: Use hot process fluids to preheat incoming process fluids | $252,728 | $102,800 |
$86,754
3,098,371
kWh
|
- | - |
$165,974
-
MMBtu
|
- | |
10 | 2.1224: Replace boiler | $10,114 | $45,600 | - | - | - |
$10,114
-
MMBtu
|
- | |
11 | 2.3212: Optimize plant power factor | $31,564 | $19,285 | - | - | $31,564 | - | - | |
TOTAL RECOMMENDED | $447,709 | $198,669 |
$105,966
3,784,534
kWh
|
$15,151
-
kW-mo/yr
|
$31,564 |
$176,926
-
MMBtu
|
$118,102
-
Tgal
|
||
TOTAL IMPLEMENTED | $22,557 | $20,963 |
$14,145
505,196
kWh
|
$8,412
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs