ITAC Assessment: UK2001
ITAC logo
ITAC Assessment: UK2001
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Dairy Products, Tea, and Fruit Juice
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 183
Plant Area 126,000
ft2
Annual Production 449,857,161
ton
Production Hrs. Annual 8,760
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $403,346 14,448,000
kWh
Electricity Demand $635,056 35,247
kW-mo/yr
Electricity Fees $23,316 -
Natural Gas $219,748 70,062
MMBtu
Waste Disposal Costs
Water Usage $366,141 90,360
Tgal
Water Disposal $447,431 41,936
Tgal
TOTAL YEARLY COSTS $2,095,038
RECOMMENDED SAVINGS* $447,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,557

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,076 $2,010 $4,292
153,300
kWh
$3,784
-
kW-mo/yr
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,413 - $512
18,287
kWh
$901
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,887 $9,378 $5,259
187,814
kWh
$4,628
-
kW-mo/yr
- - -
04 2.7135: Install occupancy sensors $571 $875 $571
20,386
kWh
- - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,684 $2,240 $3,819
136,400
kWh
$4,865
-
kW-mo/yr
- - -
06 3.4116: Meter recycled water (to reduce sewer charges) $118,102 $6,775 - - - - $118,102
-
Tgal
07 2.2615: Clean condenser tubes $4,023 $8,700 $4,023
143,696
kWh
- - - -
08 2.2511: Insulate bare equipment $2,547 $1,006 $736
26,280
kWh
$973
-
kW-mo/yr
- $838
-
MMBtu
-
09 2.2444: Use hot process fluids to preheat incoming process fluids $252,728 $102,800 $86,754
3,098,371
kWh
- - $165,974
-
MMBtu
-
10 2.1224: Replace boiler $10,114 $45,600 - - - $10,114
-
MMBtu
-
11 2.3212: Optimize plant power factor $31,564 $19,285 - - $31,564 - -
TOTAL RECOMMENDED $447,709 $198,669 $105,966
3,784,534
kWh
$15,151
-
kW-mo/yr
$31,564 $176,926
-
MMBtu
$118,102
-
Tgal
TOTAL IMPLEMENTED $22,557 $20,963 $14,145
505,196
kWh
$8,412
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs