| Assessment Year | 2018 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 4 |
| Plant Area |
150,000
ft2
|
| Annual Production | 1,250
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $27,709 | 847,320 |
kWh
|
$0.033 | |
| Electricity Demand | $28,431 | 1,426 |
kW-mo/yr
|
$19.94 | |
| Waste Disposal Costs | |||||
| Water Usage | $12,000 | 3,000 |
Tgal
|
$4.00 | |
| TOTAL YEARLY COSTS | $68,140 | ||||
| RECOMMENDED SAVINGS* | $18,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $6,703 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $247 | - |
$247
7,474
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $459 | $516 |
$172
5,224
kWh
|
$287
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $246 | $133 |
$246
7,469
kWh
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $5,751 | - |
$5,751
174,226
kWh
|
- | - | |
| 05 | 3.4159: Replace treated water with well / surface water | $11,910 | $3,700 |
$(-90.0)
2,727
kWh
|
- |
$12,000
-
Tgal
|
|
| TOTAL RECOMMENDED | $18,613 | $4,349 |
$6,326
197,120
kWh
|
$287
-
kW-mo/yr
|
$12,000
-
Tgal
|
||
| TOTAL IMPLEMENTED | $6,703 | $649 |
$6,416
194,393
kWh
|
$287
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs