Assessment Year | 2016 |
---|---|
Principal Product | Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 8 |
Plant Area |
120,000
ft2
|
Annual Production | 693,500
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $177,417 | 2,667,100 |
kWh
|
$0.067 |
Electricity Demand | $51,645 | 4,165 |
kW-mo/yr
|
$12.40 |
Electricity Fees | $1,735 | - |
|
- |
TOTAL YEARLY COSTS | $230,797 | |||
RECOMMENDED SAVINGS* | $116,203 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,816 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $53,387 | $292,000 |
$42,525
639,480
kWh
|
$10,862
-
kW-mo/yr
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $42,600 | $41,160 |
$42,600
640,000
kWh
|
- | |
03 | 2.4321: Upgrade obsolete equipment | $19,747 | $4,240 |
$15,729
236,520
kWh
|
$4,018
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $469 | $1,775 |
$258
3,875
kWh
|
$211
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $116,203 | $339,175 |
$101,112
1,519,875
kWh
|
$15,091
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $62,816 | $47,175 |
$58,587
880,395
kWh
|
$4,229
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs