| Assessment Year | 2016 |
|---|---|
| Principal Product | Waste Water Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 5 |
| Plant Area |
87,120
ft2
|
| Annual Production | 365,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,249 | 1,009,750 |
kWh
|
$0.068 |
| Electricity Demand | $22,973 | 2,367 |
kW-mo/yr
|
$9.71 |
| Electricity Fees | $634 | - |
|
- |
| TOTAL YEARLY COSTS | $91,856 | |||
| RECOMMENDED SAVINGS* | $38,652 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $19,749 | $90,000 |
$10,659
157,680
kWh
|
$2,808
-
kW-mo/yr
|
$6,282
-
lb
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,258 | $7,310 |
$2,868
42,423
kWh
|
$390
-
kW-mo/yr
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,300 | $8,440 |
$9,300
138,000
kWh
|
- | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $316 | - |
$316
4,672
kWh
|
- | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $5,013 | - |
$4,104
60,704
kWh
|
- | - | $909 | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,016 | $2,500 |
$610
9,017
kWh
|
$406
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $38,652 | $108,250 |
$27,857
412,496
kWh
|
$3,604
-
kW-mo/yr
|
$6,282
-
lb
|
$909 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs