ITAC Assessment: UK1602
ITAC logo
ITAC Assessment: UK1602
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Automotive Parts
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $50
M
to 100
M
# of Employees 340
Plant Area 305,000
ft2
Annual Production 14,750,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $654,387 10,759,653
kWh
Electricity Demand $248,956 25,915
kW-mo/yr
Electricity Fees $13,603 -
Natural Gas $49,682 6,588
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $239,477 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,037 $1,750 $13,344
204,984
kWh
$2,693
-
kW-mo/yr
- - -
02 2.4239: Eliminate or reduce compressed air usage $106,116 $60,000 $88,302
1,356,409
kWh
$17,814
-
kW-mo/yr
- - -
03 2.4221: Install compressor air intakes in coolest locations $9,180 $890 $7,741
118,916
kWh
$1,439
-
kW-mo/yr
- - -
04 2.2437: Recover waste heat from equipment $18,357 $3,168 $6,160
94,618
kWh
- $12,197
-
MMBtu
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $922 $2,336 $922
14,170
kWh
- - - -
06 2.2511: Insulate bare equipment $618 $151 $618
9,496
kWh
- - - -
07 2.7121: Utilize daylight whenever possible in lieu of artificial light $667 $209 $667
10,250
kWh
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $37,131 $80,175 $33,891
520,606
kWh
$7,365
-
kW-mo/yr
- $(-142.0) $(-3,983.0)
09 2.7111: Reduce illumination to minimum necessary levels $1,902 $805 $1,902
29,216
kWh
- - - -
10 3.1171: Change product specs $3,827 $675 - - - - $3,827
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $815 - $815
12,515
kWh
- - - -
12 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $23,450 $112,000 - - $23,450
-
MMBtu
- -
13 2.3212: Optimize plant power factor $20,455 $26,250 - - - $20,455 -
TOTAL RECOMMENDED $239,477 $288,409 $154,362
2,371,180
kWh
$29,311
-
kW-mo/yr
$35,647
-
MMBtu
$20,313 $(-156.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs