| Assessment Year | 2013 |
|---|---|
| Principal Product | Rubber O-rings |
| NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
| SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
| Sales Range | $10 M to 50M |
| # of Employees | 184 |
| Plant Area |
60,000
ft2
|
| Annual Production | 120,000
ton
|
| Production Hrs. Annual | 5,304
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $195,996 | 5,816,700 |
kWh
|
$0.034 |
| Electricity Demand | $143,776 | 11,313 |
kW-mo/yr
|
$12.71 |
| Electricity Fees | $65,890 | - |
|
- |
| Natural Gas | $5,047 | 722 |
MMBtu
|
$6.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,493 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,236 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $21,600 | - | - | - | $21,600 | - | |
| 02 | 2.6218: Turn off equipment when not in use | $11,113 | - |
$11,113
326,869
kWh
|
- | - | - | |
| 03 | 2.3212: Optimize plant power factor | $9,386 | $1,600 | - | - | $9,386 | - | |
| 04 | 2.2437: Recover waste heat from equipment | $5,885 | $3,060 | - | - | - |
$5,885
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,000 | $1,930 |
$1,600
48,000
kWh
|
$1,400
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $2,534 | $3,475 |
$1,553
42,684
kWh
|
$981
-
kW-mo/yr
|
- | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $1,429 | - |
$834
24,539
kWh
|
$595
-
kW-mo/yr
|
- | - | |
| 08 | 2.7124: Make a practice of turning off lights when not needed | $716 | $840 |
$716
21,046
kWh
|
- | - | - | |
| 09 | 2.5123: Reduce fluid flow rates | $465 | - |
$250
7,425
kWh
|
$215
-
kW-mo/yr
|
- | - | |
| 10 | 2.7135: Install occupancy sensors | $365 | $840 |
$365
10,780
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $56,493 | $11,745 |
$16,431
481,343
kWh
|
$3,191
-
kW-mo/yr
|
$30,986 |
$5,885
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $34,236 | $5,915 |
$2,269
63,730
kWh
|
$981
-
kW-mo/yr
|
$30,986 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs