ITAC Assessment: KU0200
ITAC logo
ITAC Assessment: KU0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product MASONRY HANDLING EQUIPMENT
NAICS
n/a
SIC 3546: Power-Driven Handtools
Sales Range $50
M
to 100
M
# of Employees 160
Plant Area
n/a
Annual Production 90,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,737 1,352,872
kWh
Natural Gas $33,059 8,249
MMBtu
Other Energy $7,200 1,136
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,056 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,840

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings
01 2.7111: Reduce illumination to minimum necessary levels $7,229 $14,500 $7,229
96,131
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,130 $1,000 $3,130
41,618
kWh
- -
03 2.7221: Lower temperature during the winter season and vice-versa $2,694 - $529
7,034
kWh
$2,165
-
MMBtu
-
04 2.6121: Reduce hot water temperature to the minimum required $473 - $397
5,275
kWh
$76
-
MMBtu
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $198 - $198
2,638
kWh
- -
06 2.8223: Add air shields to trucks to increase fuel mileage $216 - - - $216
-
MMBtu
07 2.2437: Recover waste heat from equipment $116 $150 - $116
-
MMBtu
-
TOTAL RECOMMENDED $14,056 $15,650 $11,483
152,696
kWh
$2,357
-
MMBtu
$216
-
MMBtu
TOTAL IMPLEMENTED $13,840 $15,650 $11,483
152,696
kWh
$2,357
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs