Assessment Year | 1986 |
---|---|
Principal Product | MASONRY HANDLING EQUIPMENT |
NAICS |
n/a
|
SIC | 3546: Power-Driven Handtools |
Sales Range | $50 M to 100M |
# of Employees | 160 |
Plant Area |
n/a
|
Annual Production | 90,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,737 | 1,352,872 |
kWh
|
$0.075 |
Natural Gas | $33,059 | 8,249 |
MMBtu
|
$4.01 |
Other Energy | $7,200 | 1,136 |
MMBtu
|
$6.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,056 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,840 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $7,229 | $14,500 |
$7,229
96,131
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,130 | $1,000 |
$3,130
41,618
kWh
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $2,694 | - |
$529
7,034
kWh
|
$2,165
-
MMBtu
|
- | |
04 | 2.6121: Reduce hot water temperature to the minimum required | $473 | - |
$397
5,275
kWh
|
$76
-
MMBtu
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $198 | - |
$198
2,638
kWh
|
- | - | |
06 | 2.8223: Add air shields to trucks to increase fuel mileage | $216 | - | - | - |
$216
-
MMBtu
|
|
07 | 2.2437: Recover waste heat from equipment | $116 | $150 | - |
$116
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $14,056 | $15,650 |
$11,483
152,696
kWh
|
$2,357
-
MMBtu
|
$216
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,840 | $15,650 |
$11,483
152,696
kWh
|
$2,357
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs