ITAC Assessment: UF0384
ITAC logo
ITAC Assessment: UF0384
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Fresh Pork
NAICS 311611: Animal (except Poultry) Slaughtering
SIC 2011: Meat Packing Plants
Sales Range $1
M
to 5
M
# of Employees 16
Plant Area 958,320
ft2
Annual Production 8,000,000
lb
Production Hrs. Annual 2,610
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,045 1,111,288
kWh
Electricity Demand $18,161 2,286
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,606 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,087 $1,070 $2,600
41,671
kWh
$487
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $2,569 $2,053 $2,569
41,168
kWh
- -
03 2.7124: Make a practice of turning off lights when not needed $117 - $117
1,872
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $8,026 - $8,026
101,207
kWh
- -
05 2.4133: Use most efficient type of electric motors $1,822 $3,057 $1,449
23,387
kWh
$373
-
kW-mo/yr
-
06 2.2511: Insulate bare equipment $1,524 $408 $1,524
19,225
kWh
- -
07 2.2691: Shut off cooling if cold outside air will cool process $2,857 $575 $2,857
36,025
kWh
- -
08 2.2511: Insulate bare equipment $25,292 $72,945 $25,292
405,316
kWh
- -
09 2.8226: Increase efficiency of trucks $2,312 - - - $2,312
TOTAL RECOMMENDED $47,606 $80,108 $44,434
669,871
kWh
$860
-
kW-mo/yr
$2,312
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs