Assessment Year | 2013 |
---|---|
Principal Product | conduit |
NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $100 M to 500M |
# of Employees | 198 |
Plant Area |
400,000
ft2
|
Annual Production | 120,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $472,753 | 13,516,800 |
kWh
|
$0.035 |
Electricity Demand | $779,634 | 64,892 |
kW-mo/yr
|
$12.01 |
Electricity Fees | $36,641 | - |
|
- |
Natural Gas | $477,424 | 113,164 |
MMBtu
|
$4.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $417,784 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $203,802 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3134: Shift from daytime to nighttime operation | $138,049 | $23,400 | - | - | $138,049 | - | |
02 | 2.4321: Upgrade obsolete equipment | $54,717 | $520,000 |
$23,587
673,920
kWh
|
$31,130
-
kW-mo/yr
|
- | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $23,264 | $5,000 |
$23,264
664,679
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,416 | $6,400 |
$12,416
356,160
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,570 | $504 |
$7,070
202,000
kWh
|
$3,500
-
kW-mo/yr
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,527 | $1,376 |
$2,477
70,780
kWh
|
$2,050
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,529 | $2,581 |
$158
4,525
kWh
|
$75
-
kW-mo/yr
|
$2,296 | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,121 | $2,121 |
$997
28,470
kWh
|
$1,124
-
kW-mo/yr
|
- | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $815 | - |
$815
23,296
kWh
|
- | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $109,909 | $9,000 |
$64,944
1,855,553
kWh
|
$44,965
-
kW-mo/yr
|
- | - | |
11 | 2.7495: Install replacement doors | $49,300 | $270,900 | - | - | - |
$49,300
-
MMBtu
|
|
12 | 2.1133: Adjust burners for efficient operation | $5,094 | $8,500 | - | - | - |
$5,094
-
MMBtu
|
|
13 | 2.2511: Insulate bare equipment | $4,473 | $3,055 | - | - | - |
$4,473
-
MMBtu
|
|
TOTAL RECOMMENDED | $417,784 | $852,837 |
$135,728
3,879,383
kWh
|
$82,844
-
kW-mo/yr
|
$140,345 |
$58,867
-
MMBtu
|
||
TOTAL IMPLEMENTED | $203,802 | $535,880 |
$122,157
3,490,228
kWh
|
$81,645
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs