ITAC Assessment: UF0642
ITAC logo
ITAC Assessment: UF0642
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Soft Drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 500
Plant Area 263,599
ft2
Annual Production 61,918
Tgal
Production Hrs. Annual 4,356
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $760,313 10,635,004
kWh
Electricity Demand $249,438 23,079
kW-mo/yr
Electricity Fees $216,205 -
Waste Disposal Costs
Water Usage $311,116 101,257
Tgal
Water Disposal $417,747 46,375
Tgal
TOTAL YEARLY COSTS $1,954,819
RECOMMENDED SAVINGS* $530,998 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $168,575 $806,620 $103,727
1,460,945
kWh
$64,848
-
kW-mo/yr
- - - - -
02 2.3191: Use demand controller or load shedder $70,317 $57,216 $52,856
744,450
kWh
$17,461
-
kW-mo/yr
- - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $29,425 - $29,425
414,438
kWh
- - - - - -
04 2.2623: Minimize condenser cooling water temperature $23,539 $28,875 $23,539
331,537
kWh
- - - - - -
05 2.4322: Use or replace with energy efficient substitutes $19,952 $69,500 $11,969
168,582
kWh
$7,983
-
kW-mo/yr
- - - - -
06 2.4133: Use most efficient type of electric motors $8,671 $20,807 $4,741
66,775
kWh
$3,930
-
kW-mo/yr
- - - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,894 - $2,509
35,340
kWh
- - - $1,188 - $1,197
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,674 $364 $2,674
37,655
kWh
- - - - - -
09 3.4154: Eliminate leaks in water lines and valves $2,045 $96 - - $520
-
Tgal
$1,525
-
Tgal
- - -
10 4.661: Level zero – install control systems for existing equipment $75,509 $60,000 $75,509
1,063,500
kWh
- - - - - -
11 4.424: Improve space comfort conditioning $66,575 $22,572 $(-1,946.0)
(-27,404)
kWh
$(-1,367.0)
-
kW-mo/yr
- - - $69,888 -
12 4.126: Install sensors to detect defects $58,822 $28,000 - - - - - $58,822 -
TOTAL RECOMMENDED $530,998 $1,094,050 $305,003
4,295,818
kWh
$92,855
-
kW-mo/yr
$520
-
Tgal
$1,525
-
Tgal
$1,188 $128,710 $1,197
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs