ITAC Assessment: UF0604
ITAC logo
ITAC Assessment: UF0604
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 10
Plant Area 540,000
ft2
Annual Production 2,226,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $633,216 7,141,473
kWh
Electricity Demand $1 13,433
kW-mo/yr
Electricity Fees $56,064 -
TOTAL YEARLY COSTS $689,281
RECOMMENDED SAVINGS* $168,933 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $119,288

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $48,311 $293,280 $48,311
542,823
kWh
-
02 2.4133: Use most efficient type of electric motors $30,577 $37,582 $30,577
343,560
kWh
-
03 2.4112: Install soft-start to eliminate nuisance trips $8,590 $37,275 $8,590
96,514
kWh
-
04 2.7243: Improve air circulation with destratification fans / other methods $3,173 - $3,173
35,650
kWh
-
05 2.7132: Install timers on light switches in little used areas $2,430 $780 $2,430
27,300
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,334 $6,383 $1,334
14,990
kWh
-
07 4.661: Level zero – install control systems for existing equipment $63,559 $10,000 $63,559
714,147
kWh
-
08 4.662: Level one – add communication using iiot devices to existing control system to modify operations $10,959 - - $10,959
TOTAL RECOMMENDED $168,933 $385,300 $157,974
1,774,984
kWh
$10,959
TOTAL IMPLEMENTED $119,288 $85,637 $108,329
1,217,171
kWh
$10,959
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs