ITAC Assessment: UF0595
ITAC logo
ITAC Assessment: UF0595
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Brass and Aluminum Foundry
NAICS 331529: Other Nonferrous Metal Foundries (except Die-Casting)
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $10
M
to 50
M
# of Employees 145
Plant Area 75,048
ft2
Annual Production 104,260
units
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $188,845 3,863,370
kWh
Electricity Demand $207,537 12,649
kW-mo/yr
Electricity Fees $10,534 -
Natural Gas $17,683 1,184
MMBtu
TOTAL YEARLY COSTS $424,599
RECOMMENDED SAVINGS* $192,353 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,724

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.9114: Use solar heat to make electricty $95,368 $289,896 $32,365
660,510
kWh
$63,003
-
kW-mo/yr
- -
02 2.3191: Use demand controller or load shedder $39,683 $20,785 $18,931
386,337
kWh
$20,752
-
kW-mo/yr
- -
03 2.6231: Utilize controls to operate equipment only when needed $18,931 $25,400 $18,931
386,337
kWh
- - -
04 2.3142: User battery storage for power quality issues $6,261 $20,000 $4,292
87,600
kWh
$1,969
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,458 $356 $4,458
90,978
kWh
- - -
06 2.7141: Lower light fixtures in high ceiling areas $2,957 $3,276 $1,575
32,124
kWh
$1,382
-
kW-mo/yr
- -
07 2.8117: Install sub-metering equipment $1,589 $4,340 - - $1,589
-
MMBtu
-
08 2.2623: Minimize condenser cooling water temperature $1,317 $5,838 $1,317
26,885
kWh
- - -
09 2.7135: Install occupancy sensors $1,092 $2,160 $1,092
22,292
kWh
- - -
10 4.424: Improve space comfort conditioning $20,697 $4,480 $(-3,220.0)
(-65,707)
kWh
$(-2,073.0)
-
kW-mo/yr
- $25,990
TOTAL RECOMMENDED $192,353 $376,531 $79,741
1,627,356
kWh
$85,033
-
kW-mo/yr
$1,589
-
MMBtu
$25,990
TOTAL IMPLEMENTED $90,724 $66,635 $43,084
879,246
kWh
$20,061
-
kW-mo/yr
$1,589
-
MMBtu
$25,990
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs