| Assessment Year | 2023 |
|---|---|
| Principal Product | Insulated Panels |
| NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
| SIC | 3448: Prefabricated Metal Buildings and Components |
| Sales Range | $10 M to 50M |
| # of Employees | 93 |
| Plant Area |
197,000
ft2
|
| Annual Production | 15,716,000
thousand feet
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $145,388 | 2,049,157 |
kWh
|
$0.071 | |
| Electricity Demand | $58,978 | 9,328 |
kW-mo/yr
|
$6.32 | |
| Electricity Fees | $39,058 | - |
|
- | |
| Natural Gas | $68,095 | 9,374 |
MMBtu
|
$7.26 | |
| LPG | $36,612 | 1,374 |
MMBtu
|
$26.65 | |
| Waste Disposal Costs | |||||
| Water Usage | $6,611 | 160,000 |
Tgal
|
$0.041 | |
| Solid Waste (non-haz) | $24,000 | 36,000 |
lb
|
$0.67 | |
| TOTAL YEARLY COSTS | $378,742 | ||||
| RECOMMENDED SAVINGS* | $201,634 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $24,607 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $133,034 | $448,875 |
$178,358
2,512,079
kWh
|
$26,557
-
kW-mo/yr
|
$84,270
-
MMBtu
|
$(-156,151.0) | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $17,027 | $20,000 | - | - |
$17,027
-
MMBtu
|
- | - | |
| 03 | 2.3191: Use demand controller or load shedder | $14,312 | $11,024 |
$10,184
143,441
kWh
|
$4,128
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7425: Clean or color roof to reduce solar load | $8,425 | $36,450 |
$8,425
118,657
kWh
|
- | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $4,229 | - |
$4,229
59,557
kWh
|
- | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,086 | $356 |
$4,086
57,554
kWh
|
- | - | - | - | |
| 07 | 4.424: Improve space comfort conditioning | $15,247 | $4,480 |
$(-5,794.0)
(-81,600)
kWh
|
$(-799.0)
-
kW-mo/yr
|
- | - | $21,840 | |
| 08 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $5,274 | - | - | - | - | $5,274 | - | |
| TOTAL RECOMMENDED | $201,634 | $521,185 |
$199,488
2,809,688
kWh
|
$29,886
-
kW-mo/yr
|
$101,297
-
MMBtu
|
$(-150,877.0) | $21,840 | ||
| TOTAL IMPLEMENTED | $24,607 | $4,836 |
$(-1,708.0)
(-24,046)
kWh
|
$(-799.0)
-
kW-mo/yr
|
- | $5,274 | $21,840 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs