ITAC Assessment: UF0583
ITAC logo
ITAC Assessment: UF0583
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Intraocular Lenses
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $100
M
to 500
M
# of Employees 60
Plant Area 102,000
ft2
Annual Production 4,286,708
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $589,014 11,524,402
kWh
Electricity Demand $54,927 18,109
kW-mo/yr
Electricity Fees $103,998 -
Waste Disposal Costs
Water Usage $142,554 12,033
Tgal
Water Disposal $162,082 12,033
Tgal
TOTAL YEARLY COSTS $1,052,575
RECOMMENDED SAVINGS* $713,996 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $381,249

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $308,276 $1,243,750 $486,462
9,538,462
kWh
$47,315
-
kW-mo/yr
$(-115,001.0)
-
MMBtu
- $(-110,500.0)
02 2.3191: Use demand controller or load shedder $44,987 $62,001 $41,142
806,708
kWh
$3,845
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $14,746 $33,000 $13,633
267,321
kWh
$1,113
-
kW-mo/yr
- - -
04 2.2625: Chill water to the highest temperature possible $13,240 - $13,240
259,616
kWh
- - - -
05 4.662: Level one – add communication using iiot devices to existing control system to modify operations $273,973 - - - - $273,973 -
06 4.661: Level zero – install control systems for existing equipment $58,774 $10,000 $58,774
1,152,440
kWh
- - - -
TOTAL RECOMMENDED $713,996 $1,348,751 $613,251
12,024,547
kWh
$52,273
-
kW-mo/yr
$(-115,001.0)
-
MMBtu
$273,973 $(-110,500.0)
TOTAL IMPLEMENTED $381,249 $1,338,751 $554,477
10,872,107
kWh
$52,273
-
kW-mo/yr
$(-115,001.0)
-
MMBtu
- $(-110,500.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs