ITAC Assessment: UF0581
ITAC logo
ITAC Assessment: UF0581
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $500
k
to 1
M
# of Employees 7
Plant Area 131,250
ft2
Annual Production 663,330
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,916 1,077,240
kWh
Natural Gas $11,368 21,785
MMBtu
TOTAL YEARLY COSTS $126,284
RECOMMENDED SAVINGS* $128,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,396

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings By-product Production Savings
01 2.9114: Use solar heat to make electricty $74,168 $293,280 $74,168
693,160
kWh
- - -
02 2.4133: Use most efficient type of electric motors $17,084 $4,202 $17,084
159,669
kWh
- - -
03 2.3191: Use demand controller or load shedder $8,046 $5,794 $8,046
75,407
kWh
- - -
04 2.4112: Install soft-start to eliminate nuisance trips $5,091 $8,250 $5,091
47,578
kWh
- - -
05 4.661: Level zero – install control systems for existing equipment $11,526 $10,000 $11,526
107,724
kWh
- - -
06 4.664: Level three - install or modify control system with communication and nonlocal external information (i.e. weather foreca $3,458 $11,225 $3,458
32,317
kWh
- - -
07 4.662: Level one – add communication using iiot devices to existing control system to modify operations $2,191 - - - $2,191 -
08 3.5217: Reuse / recycle/ sell paper products $6,981 $27,240 $(-9,461.0)
(-88,425)
kWh
$(-115.0)
-
MMBtu
- $16,557
TOTAL RECOMMENDED $128,545 $359,991 $109,912
1,027,430
kWh
$(-115.0)
-
MMBtu
$2,191 $16,557
TOTAL IMPLEMENTED $47,396 $39,471 $45,205
422,695
kWh
- $2,191 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs