ITAC Assessment: UF0573
ITAC logo
ITAC Assessment: UF0573
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 10
Plant Area 2,217,000
ft2
Annual Production 1,829,900
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $357,244 9,450,400
kWh
Electricity Demand $149,179 32,695
kW-mo/yr
Electricity Fees $16,107 -
TOTAL YEARLY COSTS $522,530
RECOMMENDED SAVINGS* $674,666 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $674,666

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
01 2.3322: Use existing dam to generate electricity $223,605 $552,197 $212,800
5,600,000
kWh
$43,805
-
kW-mo/yr
$(-33,000.0) - -
02 2.4133: Use most efficient type of electric motors $50,619 $45,817 $37,592
989,267
kWh
$13,027
-
kW-mo/yr
- - -
03 2.3191: Use demand controller or load shedder $35,580 $50,843 $25,138
661,528
kWh
$10,442
-
kW-mo/yr
- - -
04 4.111: Add equipment/ operators to reduce production bottleneck $324,658 $1,232,000 $(-7,450.0)
(-196,049)
kWh
$(-1,225.0)
-
kW-mo/yr
- - $333,333
05 4.661: Level zero – install control systems for existing equipment $35,912 $10,000 $35,912
945,040
kWh
- - - -
06 4.662: Level one – add communication using iiot devices to existing control system to modify operations $4,292 - - - - $4,292 -
TOTAL RECOMMENDED $674,666 $1,890,857 $303,992
7,999,786
kWh
$66,049
-
kW-mo/yr
$(-33,000.0) $4,292 $333,333
TOTAL IMPLEMENTED $674,666 $1,890,857 $303,992
7,999,786
kWh
$66,049
-
kW-mo/yr
$(-33,000.0) $4,292 $333,333
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs