| Assessment Year | 2022 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 10 |
| Plant Area |
2,217,000
ft2
|
| Annual Production | 1,829,900
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $357,244 | 9,450,400 |
kWh
|
$0.038 |
| Electricity Demand | $149,179 | 32,695 |
kW-mo/yr
|
$4.56 |
| Electricity Fees | $16,107 | - |
|
- |
| TOTAL YEARLY COSTS | $522,530 | |||
| RECOMMENDED SAVINGS* | $674,666 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $674,666 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3322: Use existing dam to generate electricity | $223,605 | $552,197 |
$212,800
5,600,000
kWh
|
$43,805
-
kW-mo/yr
|
$(-33,000.0) | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $50,619 | $45,817 |
$37,592
989,267
kWh
|
$13,027
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.3191: Use demand controller or load shedder | $35,580 | $50,843 |
$25,138
661,528
kWh
|
$10,442
-
kW-mo/yr
|
- | - | - | |
| 04 | 4.111: Add equipment/ operators to reduce production bottleneck | $324,658 | $1,232,000 |
$(-7,450.0)
(-196,049)
kWh
|
$(-1,225.0)
-
kW-mo/yr
|
- | - | $333,333 | |
| 05 | 4.661: Level zero – install control systems for existing equipment | $35,912 | $10,000 |
$35,912
945,040
kWh
|
- | - | - | - | |
| 06 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $4,292 | - | - | - | - | $4,292 | - | |
| TOTAL RECOMMENDED | $674,666 | $1,890,857 |
$303,992
7,999,786
kWh
|
$66,049
-
kW-mo/yr
|
$(-33,000.0) | $4,292 | $333,333 | ||
| TOTAL IMPLEMENTED | $674,666 | $1,890,857 |
$303,992
7,999,786
kWh
|
$66,049
-
kW-mo/yr
|
$(-33,000.0) | $4,292 | $333,333 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs