Assessment Year | 2021 |
---|---|
Principal Product | Metal Plate Connected Wood Trusses |
NAICS | 321992: Prefabricated Wood Building Manufacturing |
SIC | 2452: Prefabricated Wood Buildings and Components |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
750,000
ft2
|
Annual Production | 19,062,763
units
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $184,947 | 1,038,906 |
kWh
|
$0.18 | |
LPG | $28,980 | 1,270 |
MMBtu
|
$22.82 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $30,530 | 1,920,106 |
lb
|
$0.016 | |
TOTAL YEARLY COSTS | $244,457 | ||||
RECOMMENDED SAVINGS* | $39,068 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $14,617 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $24,451 | $95,589 |
$24,451
137,367
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,895 | $3,125 |
$5,895
33,120
kWh
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $3,163 | - |
$3,163
17,772
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,026 | $406 |
$3,026
17,000
kWh
|
- | - | |
05 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,582 | $735 |
$1,582
8,886
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $951 | - |
$507
2,851
kWh
|
$263 | $181 | |
TOTAL RECOMMENDED | $39,068 | $99,855 |
$38,624
216,996
kWh
|
$263 | $181 | ||
TOTAL IMPLEMENTED | $14,617 | $4,266 |
$14,173
79,629
kWh
|
$263 | $181 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs