Assessment Year | 2021 |
---|---|
Principal Product | Concrete Septic Tanks |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
4,900,000
ft2
|
Annual Production | 18,434
ton
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $14,241 | 191,497 |
kWh
|
$0.074 | |
Electricity Demand | $6,744 | 603 |
kW-mo/yr
|
$11.18 | |
Electricity Fees | $5,319 | - |
|
- | |
Fuel Oil #2 | $142,749 | 7,578 |
MMBtu
|
$18.84 | |
Waste Disposal Costs | |||||
Water Usage | $5,419 | 585 |
Tgal
|
$9.26 | |
TOTAL YEARLY COSTS | $174,472 | ||||
RECOMMENDED SAVINGS* | $423,317 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $423,317 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8226: Increase efficiency of trucks | $70,950 | $336,000 | - | - |
$46,950
-
MMBtu
|
$24,000 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,846 | $7,217 |
$2,952
39,893
kWh
|
$4,894
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $2,700 | $10,047 |
$2,700
36,481
kWh
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $1,821 | $3,900 |
$581
7,849
kWh
|
$1,240
-
kW-mo/yr
|
- | - | - | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $340,000 | $5,859 | - | - | - | - | $340,000 | |
TOTAL RECOMMENDED | $423,317 | $363,023 |
$6,233
84,223
kWh
|
$6,134
-
kW-mo/yr
|
$46,950
-
MMBtu
|
$24,000 | $340,000 | ||
TOTAL IMPLEMENTED | $423,317 | $363,023 |
$6,233
84,223
kWh
|
$6,134
-
kW-mo/yr
|
$46,950
-
MMBtu
|
$24,000 | $340,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs