ITAC Assessment: UF0555
ITAC logo
ITAC Assessment: UF0555
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Concrete Septic Tanks
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 4,900,000
ft2
Annual Production 18,434
ton
Production Hrs. Annual 2,860
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,241 191,497
kWh
Electricity Demand $6,744 603
kW-mo/yr
Electricity Fees $5,319 -
Fuel Oil #2 $142,749 7,578
MMBtu
Waste Disposal Costs
Water Usage $5,419 585
Tgal
TOTAL YEARLY COSTS $174,472
RECOMMENDED SAVINGS* $423,317 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $423,317

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 2.8226: Increase efficiency of trucks $70,950 $336,000 - - $46,950
-
MMBtu
$24,000 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,846 $7,217 $2,952
39,893
kWh
$4,894
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $2,700 $10,047 $2,700
36,481
kWh
- - - -
04 2.4133: Use most efficient type of electric motors $1,821 $3,900 $581
7,849
kWh
$1,240
-
kW-mo/yr
- - -
05 4.111: Add equipment/ operators to reduce production bottleneck $340,000 $5,859 - - - - $340,000
TOTAL RECOMMENDED $423,317 $363,023 $6,233
84,223
kWh
$6,134
-
kW-mo/yr
$46,950
-
MMBtu
$24,000 $340,000
TOTAL IMPLEMENTED $423,317 $363,023 $6,233
84,223
kWh
$6,134
-
kW-mo/yr
$46,950
-
MMBtu
$24,000 $340,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs