| Assessment Year | 2020 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 17 |
| Plant Area |
1,203,500
ft2
|
| Annual Production | 1,901,650
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $359,618 | 11,065,169 |
kWh
|
$0.033 |
| Electricity Demand | $117,488 | 19,746 |
kW-mo/yr
|
$5.95 |
| TOTAL YEARLY COSTS | $477,106 | |||
| RECOMMENDED SAVINGS* | $147,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $72,645 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.9141: Install anaerobic digester | $74,732 | $250,000 |
$28,096
878,000
kWh
|
- |
$46,636
-
MMBtu
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $19,805 | $25,232 |
$13,509
422,146
kWh
|
$6,296
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4112: Install soft-start to eliminate nuisance trips | $6,420 | $17,086 |
$6,420
200,616
kWh
|
- | - | - | - | |
| 04 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $9,363 | - | - | - | - | $9,363 | - | |
| 05 | 4.126: Install sensors to detect defects | $3,851 | $15,420 |
$3,851
120,352
kWh
|
- | - | - | - | |
| 06 | 3.4156: Use flow control valves on equipment to optimize water use | $30,206 | $6,500 |
$30,206
943,939
kWh
|
- | - | - | - | |
| 07 | 3.7196: Use re-usable filters | $3,000 | $1,906 | - | - | - | - | $3,000 | |
| TOTAL RECOMMENDED | $147,377 | $316,144 |
$82,082
2,565,053
kWh
|
$6,296
-
kW-mo/yr
|
$46,636
-
MMBtu
|
$9,363 | $3,000 | ||
| TOTAL IMPLEMENTED | $72,645 | $66,144 |
$53,986
1,687,053
kWh
|
$6,296
-
kW-mo/yr
|
- | $9,363 | $3,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs