ITAC Assessment: UF0549
ITAC logo
ITAC Assessment: UF0549
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Reclaimed Water and Bio-Solids
NAICS 221118: Other Electric Power Generation
SIC 4939: Combination Utilities, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 3,384,000
ft2
Annual Production 14,391,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,482,684 42,058,447
kWh
Electricity Demand $752,541 90,493
kW-mo/yr
Electricity Fees $80,533 -
Natural Gas $25,570 8,597
MMBtu
Fuel Oil #1 $15,540 1,097
MMBtu
TOTAL YEARLY COSTS $3,356,868
RECOMMENDED SAVINGS* $1,308,571 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Raw Material Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $737,260 $2,600,000 $1,003,000
17,000,000
kWh
$199,584
-
kW-mo/yr
$(-295,324.0)
-
MMBtu
$(-170,000.0) -
02 2.4133: Use most efficient type of electric motors $73,018 $68,138 $54,885
930,251
kWh
$18,133
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,001 $2,904 $4,484
76,000
kWh
$1,517
-
kW-mo/yr
- - -
04 4.122: Develop standard procedures to improve internal yields $492,292 $1,875,550 $(-6,461.0)
(-109,500)
kWh
$(-1,247.0)
-
kW-mo/yr
- - $500,000
TOTAL RECOMMENDED $1,308,571 $4,546,592 $1,055,908
17,896,751
kWh
$217,987
-
kW-mo/yr
$(-295,324.0)
-
MMBtu
$(-170,000.0) $500,000
TOTAL IMPLEMENTED $6,001 $2,904 $4,484
76,000
kWh
$1,517
-
kW-mo/yr
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs