Assessment Year | 2020 |
---|---|
Principal Product | Reclaimed Water and Bio-Solids |
NAICS | 221118: Other Electric Power Generation |
SIC | 4939: Combination Utilities, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
3,384,000
ft2
|
Annual Production | 14,391,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,482,684 | 42,058,447 |
kWh
|
$0.059 |
Electricity Demand | $752,541 | 90,493 |
kW-mo/yr
|
$8.32 |
Electricity Fees | $80,533 | - |
|
- |
Natural Gas | $25,570 | 8,597 |
MMBtu
|
$2.97 |
Fuel Oil #1 | $15,540 | 1,097 |
MMBtu
|
$14.17 |
TOTAL YEARLY COSTS | $3,356,868 | |||
RECOMMENDED SAVINGS* | $1,308,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,001 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $737,260 | $2,600,000 |
$1,003,000
17,000,000
kWh
|
$199,584
-
kW-mo/yr
|
$(-295,324.0)
-
MMBtu
|
$(-170,000.0) | - | |
02 | 2.4133: Use most efficient type of electric motors | $73,018 | $68,138 |
$54,885
930,251
kWh
|
$18,133
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,001 | $2,904 |
$4,484
76,000
kWh
|
$1,517
-
kW-mo/yr
|
- | - | - | |
04 | 4.122: Develop standard procedures to improve internal yields | $492,292 | $1,875,550 |
$(-6,461.0)
(-109,500)
kWh
|
$(-1,247.0)
-
kW-mo/yr
|
- | - | $500,000 | |
TOTAL RECOMMENDED | $1,308,571 | $4,546,592 |
$1,055,908
17,896,751
kWh
|
$217,987
-
kW-mo/yr
|
$(-295,324.0)
-
MMBtu
|
$(-170,000.0) | $500,000 | ||
TOTAL IMPLEMENTED | $6,001 | $2,904 |
$4,484
76,000
kWh
|
$1,517
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs