ITAC Assessment: UF0540
ITAC logo
ITAC Assessment: UF0540
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Reclaimed Water and Bio-Solids
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 52
Plant Area 1,525,000
ft2
Annual Production 45,000,000
Tgal
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,463,934 28,473,059
kWh
Electricity Demand $568,049 96,283
kW-mo/yr
Electricity Fees $(-370,463.0) -
Natural Gas $381,587 69,245
MMBtu
TOTAL YEARLY COSTS $2,043,107
RECOMMENDED SAVINGS* $331,342 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $331,342

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $128,693 $34,812 - - $128,693
-
MMBtu
02 2.1331: Burn a less expensive grade of fuel $99,716 $392,375 - - $99,716
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $35,477 $20,256 $27,832
545,730
kWh
$7,645
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $32,246 $1,280 $32,246
632,284
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $16,996 - $16,996
324,075
kWh
- -
06 2.7226: Use computer programs to optimize hvac performance $18,214 $25,600 $18,214
357,139
kWh
- -
TOTAL RECOMMENDED $331,342 $474,323 $95,288
1,859,228
kWh
$7,645
-
kW-mo/yr
$228,409
-
MMBtu
TOTAL IMPLEMENTED $331,342 $474,323 $95,288
1,859,228
kWh
$7,645
-
kW-mo/yr
$228,409
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs