| Assessment Year | 2019 |
|---|---|
| Principal Product | Reclaimed Water and Bio-Solids |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 52 |
| Plant Area |
1,525,000
ft2
|
| Annual Production | 45,000,000
Tgal
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,463,934 | 28,473,059 |
kWh
|
$0.051 |
| Electricity Demand | $568,049 | 96,283 |
kW-mo/yr
|
$5.90 |
| Electricity Fees | $(-370,463.0) | - |
|
- |
| Natural Gas | $381,587 | 69,245 |
MMBtu
|
$5.51 |
| TOTAL YEARLY COSTS | $2,043,107 | |||
| RECOMMENDED SAVINGS* | $331,342 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $331,342 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $128,693 | $34,812 | - | - |
$128,693
-
MMBtu
|
|
| 02 | 2.1331: Burn a less expensive grade of fuel | $99,716 | $392,375 | - | - |
$99,716
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,477 | $20,256 |
$27,832
545,730
kWh
|
$7,645
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $32,246 | $1,280 |
$32,246
632,284
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,996 | - |
$16,996
324,075
kWh
|
- | - | |
| 06 | 2.7226: Use computer programs to optimize hvac performance | $18,214 | $25,600 |
$18,214
357,139
kWh
|
- | - | |
| TOTAL RECOMMENDED | $331,342 | $474,323 |
$95,288
1,859,228
kWh
|
$7,645
-
kW-mo/yr
|
$228,409
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $331,342 | $474,323 |
$95,288
1,859,228
kWh
|
$7,645
-
kW-mo/yr
|
$228,409
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs