Assessment Year | 2019 |
---|---|
Principal Product | Dairy Products |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2024: Ice Cream and Frozen Desserts |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
220,000
ft2
|
Annual Production | 70,000
Tgal
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $892,704 | 14,009,996 |
kWh
|
$0.064 | |
Electricity Demand | $255,104 | 30,965 |
kW-mo/yr
|
$8.24 | |
Electricity Fees | $1,272 | - |
|
- | |
Natural Gas | $146,968 | 51,084 |
MMBtu
|
$2.88 | |
Waste Disposal Costs | |||||
Water Usage | $83,848 | 50,773 |
Tgal
|
$1.65 | |
Water Disposal | $412,987 | 44,847 |
Tgal
|
$9.21 | |
TOTAL YEARLY COSTS | $1,792,883 | ||||
RECOMMENDED SAVINGS* | $28,410 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $12,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2522: Isolate hot or cold equipment | $6,559 | $10,250 |
$6,559
102,960
kWh
|
- | |
02 | 2.1222: Install turbulators | $5,011 | $7,500 | - |
$5,011
-
MMBtu
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,410 | $1,400 | - |
$4,410
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,248 | $456 |
$3,248
50,990
kWh
|
- | |
05 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $3,168 | $6,439 |
$3,168
49,733
kWh
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,284 | $3,000 |
$2,284
35,854
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $2,054 | $1,025 |
$2,054
32,246
kWh
|
- | |
08 | 2.1117: Relocate oven / furnace to more efficient location | $1,676 | $5,000 | - |
$1,676
-
MMBtu
|
|
TOTAL RECOMMENDED | $28,410 | $35,070 |
$17,313
271,783
kWh
|
$11,097
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,597 | $11,981 |
$7,586
119,090
kWh
|
$5,011
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs