ITAC Assessment: UF0521
ITAC logo
ITAC Assessment: UF0521
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Frozen Fruit and Vegetable Juices
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 68,000
ft2
Annual Production 8,000
Tgal
Production Hrs. Annual 3,432
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $386,610 4,372,200
kWh
Electricity Demand $104,802 15,480
kW-mo/yr
Electricity Fees $33,557 -
Natural Gas $128,751 15,473
MMBtu
Waste Disposal Costs
Water Usage $32,599 7,975
Tgal
Water Disposal $45,255 7,975
Tgal
TOTAL YEARLY COSTS $731,574
RECOMMENDED SAVINGS* $407,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $407,909

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings By-product Production Savings
01 2.2121: Increase amount of condensate returned $45,855 $11,386 - $21,557
-
MMBtu
$10,269
-
Tgal
$14,029
-
Tgal
- -
02 2.9114: Use solar heat to make electricty $41,132 $314,072 $41,132
465,292
kWh
- - - - -
03 2.2135: Repair and eliminate steam leaks $13,844 $562 - $13,844
-
MMBtu
- - - -
04 2.2414: Use waste heat from hot flue gases to preheat $10,195 $15,000 - $10,195
-
MMBtu
- - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,972 $4,143 $7,972
90,587
kWh
- - - - -
06 2.1116: Improve combustion control capability $3,586 $2,800 - $3,586
-
MMBtu
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,356 - $1,356
15,339
kWh
- - - - -
08 2.7135: Install occupancy sensors $1,160 $1,149 $1,160
13,179
kWh
- - - - -
09 4.514: Re-arrange equipment layout to reduce handling costs $39,645 $66,000 $38,475
437,220
kWh
- - - $1,170 -
10 3.1182: Make a new by-product $243,164 $58,810 - - - - - $243,164
TOTAL RECOMMENDED $407,909 $473,922 $90,095
1,021,617
kWh
$49,182
-
MMBtu
$10,269
-
Tgal
$14,029
-
Tgal
$1,170 $243,164
TOTAL IMPLEMENTED $407,909 $473,922 $90,095
1,021,617
kWh
$49,182
-
MMBtu
$10,269
-
Tgal
$14,029
-
Tgal
$1,170 $243,164
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs